Substation Scout

Tennessee Gas-East Towanda substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Tennessee Gas-East Towanda as the point of interconnection, all in Bradford County, PA.

Target commercial operation date as filed: Dec 2027 (2 filings).

Transmission owner as filed: PENELEC (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG2-206 Tennessee Gas-East Towanda 115 kV 115 28.8 Solar Withdrawn Dec 2027
AG2-327 Tennessee Gas-East Towanda 115 kV 115 6 Solar Withdrawn Dec 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Bradford County, PA

All 52 PJM queue filings in Bradford County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first