Union, NJ interconnection queue
22 active projects totalling 3,758.8 MW in the PJM queue, plus 18 with terminal status (shown greyed).
22active projects
3,758.8active MW
40total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| Y2-013 | Linden VFT-Tosco 230kV | 230 | 800 | Gas | Withdrawn |
| A04 | Linden 1, 2 & 3 | 230 | 750 | Gas | In Service |
| A48 | East Towanda 230kV | 230 | 750 | Gas | Withdrawn |
| C01-1495 | Linden 345 kV | 345 | 750 | Gas | Active |
| Q74 | Linden 230kV | 230 | 600 | Other | Withdrawn |
| O63 | Linden 230kV | 230 | 525 | Gas | Withdrawn |
| O13 | Linden - Harbor Cable II | n/r | 520 | Not reported | Withdrawn |
| C01 | Linden 1, 2 & 3 | 138 | 436 | Gas | In Service |
| G32_MTX6 | Linden 230kV, 138kV | 230 | 365 | Not reported | Withdrawn |
| G22_MTX5 | Linden VFT | 230 | 330 | Not reported | In Service |
| A17 | Linden 230 kV | 230 | 300 | Gas | Withdrawn |
| U2-077 | Linden VFT | 230 | 300 | Not reported | In Service |
| AA2-183 | Tosco-VFT 230kV | 230 | 230 | Gas | Withdrawn |
| Z1-109 | Tosco-VFT 230kV | 230 | 208 | Gas | Withdrawn |
| C01-1996 | North Ave 345 kV | 345 | 200 | Battery | Active |
| A26 | Tosco #6 | n/r | 180 | Gas | In Service |
| A52 | Linden | n/r | 180 | Gas | Withdrawn |
| Y1-026 | Tosco #6 | 230 | 160 | Gas | In Service |
| AH1-722 | Linden 230kV | 230 | 158.1 | Gas | Active |
| AH1-715 | Linden 138kV & 230kV | 138 | 149.4 | Gas | Active |
| A03 | Linden 5 & 6 | 230 | 120 | Gas | In Service |
| Y3-108 | Linden 230kV | 230 | 107 | Gas | Withdrawn |
| Z2-002 | Linden Generating Station | 230 | 54 | Gas | In Service |
| T77 | Linden 1 & 2 | 230 | 44 | Gas | In Service |
| Z1-058 | Linden Generating Station | 138 | 36 | Gas | In Service |
| S61 | Tosco #6 | 230 | 20 | Gas | In Service |
| Z1-059 | Linden Generating Station | 230 | 18 | Gas | In Service |
| W1-001 | Linden VFT | 230 | 15 | Not reported | In Service |
| G18 | Linden 5 & 6 | n/r | 12 | Gas | In Service |
| G19 | Linden 7 & 8 | n/r | 12 | Gas | In Service |
| X4-044 | EF Kenilworth LLC | 230 | 9.9 | Gas | In Service |
| Y3-046 | Linden Generating Station | n/r | 6 | Gas | Withdrawn |
| Y3-051 | Linden Generating Station | n/r | 4 | Gas | In Service |
| AC1-066 | Linden 26 kV | 26 | 2 | Gas | Withdrawn |
| X2-087 | Food Bank Solar | 13 | 0.4 | Solar | In Service |
| AA2-114 | Furnace Brook-Hazen Switch Point 34kV | 34 | 0 | Battery | Withdrawn |
| AC1-037 | Hillside Battery | 13 | 0 | Battery | Withdrawn |
| AC1-198 | Union 480v | n/r | 0 | Gas | Withdrawn |
| AD1-001 | Kilmer 480V | n/r | 0 | Gas | Withdrawn |
| S104 | Linden 230kV | 230 | 0 | Not reported | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.