Clover substation interconnection queue

2 active projects totalling 118.7 MW in the PJM queue, plus 5 with terminal status (shown greyed).

2active projects
118.7active MW
7total filed
Queue IDProjectkVMWResourceStatus
AF1-310 Clover 230 kV 230 114 Solar Withdrawn
AG2-270 Clover 230 kV 230 105 Battery Active
AF2-266 Clover 230 kV 230 50 Battery Withdrawn
S78 Clover 230kV 230 19 Coal Withdrawn
S77 Clover 230kV 230 16 Coal Withdrawn
Y2-076 Clover Power Station Unit 1 230 13.7 Coal In Service
W4-001 Clover n/r 5 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.