Substation Scout

Clover 230 kV

PJM queue ID AG2-270

Queue IDAG2-270
Project nameClover 230 kV
Status (as published)Active
SubstationClover
Point of interconnectionClover 230 kV
CountyHalifax
StateVA
Voltage230 kV
Capacity105 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperClover Storage, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StagePhase 3
Mw Energy150.0
Mw Capacity105.0
Mfo150.0
Submitted Date3/19/2021
Last Updated9/1/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.