Dryburg substation interconnection queue
2 active projects totaling 28.2 MW in the PJM queue.
2 PJM queue filings name Dryburg as the point of interconnection, all in Halifax County, VA.
Target commercial operation dates as filed run from Dec 2027 to May 2030 (2 filings). 2 active filings target a date after November 27, 2026.
Transmission owner as filed: Dominion (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG1-342 | Staunton Solar | 115 | 21.6 | Solar | EP | May 2030 |
| AG2-262 | Dryburg 115 kV | 115 | 6.6 | Solar | Active | Dec 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Dryburg (DOM, 1 mention).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Halifax County, VA
- Clover-Rawlings: 2 active, 420 MW of 4 filed
- Clover: 2 active, 118.7 MW of 7 filed
- Clover-Sedge Hill: 3 active, 104.5 MW of 3 filed
- Halifax-Person: 3 active, 84.8 MW of 3 filed
- Perth-Hickory Grove: 2 active, 51.1 MW of 2 filed
- Crystal Hill-Halifax: 2 active, 38.8 MW of 2 filed
- Welco: 1 active, 12 MW of 2 filed
- Crystal Hill - Perth: 1 active, 10.4 MW of 2 filed
- SedgeHill - Person: none active of 3 filed
- Sedge Hill: none active of 2 filed
- Sedge Hill - Person: none active of 2 filed
- Sinai: none active of 2 filed
- South Boston: none active of 2 filed