Biers Run-Circleville substation interconnection queue

3 active projects totaling 138.7 MW in the PJM queue, plus 3 with terminal status (shown grayed).

6 PJM queue filings name Biers Run-Circleville as the point of interconnection, all in OH.

Target commercial operation dates as filed run from Dec 2021 to May 2025 (6 filings).

3active projects
138.7active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
AD2-162 Scioto Farms Solar Project 138 73.8 Solar Withdrawn May 2025
AC2-059 Yellowbud Solar 138 62.5 Solar In Service Dec 2022
AD2-016 Yellowbud Solar 138 62.5 Solar In Service Dec 2022
AI2-249 Biers Run-Circleville 138 kV 138 40 Solar Withdrawn Apr 2023
AE2-327 Biers Run-Circleville 138 kV 138 31.3 Battery Withdrawn Dec 2021
AD1-072 Yellowbud Solar 138 13.7 Solar In Service Dec 2022

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Pickaway County, OH

All 35 PJM queue filings in Pickaway County, OH.

Other PJM queue substations in Ross County, OH

All 24 PJM queue filings in Ross County, OH.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first