Substation Scout

Yellowbud Solar

PJM queue ID AD1-072

Queue IDAD1-072
Project nameYellowbud Solar
Status (as published)In Service
SubstationBiers Run-Circleville
Point of interconnectionBiers Run-Circleville 138 kV
CountyRoss
StateOH
Voltage138 kV
Capacity13.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity13.7
Mfo147