Substation Scout

Hillsboro-Clinton substation interconnection queue

1 active project totalling 58.1 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
58.1active MW
2total filed
Queue IDProjectkVMWResourceStatus
AC2-061 Dodson Creek Solar 138 58.1 Solar In Service
AI2-252 Hillsboro-Clinton 138kV 138 20 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.