Named in 3 PJM planning documents for 2 projects, from October 8, 2025 to July 17, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
3mentions

Also printed as: New Departure Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Departure 345 kV Customer Connection
ATSI-2024-056 · s3660.1
Not printed $99.1 M November 28, 2029 Not printed 2025-10-08
TEAC
Greenfield Substation
ATSI-2026-047
Not printed Not printed Not printed Not printed 2026-07-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2025 RTEP p. 29
New Departure 345 kV Customer Connection “Adjust relay settings at New Departure Substation”
138 kV
2026-07-17 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 5
Greenfield Substation No role wording
138 kV
2025-10-08 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 29
New Departure 345 kV Customer Connection “Adjust relay settings at New Departure Substation”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.