Substation Scout

Washington

Named in 2 PJM planning documents for 1 project, from October 18, 2024 to July 17, 2026.

Not stateddescribed as
ATSIzone
69 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Black River – Shinrock 69 kV Line
ATSI-2024-072
Conceptual $67.65M 12/31/2029 Not printed 2026-07-17
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named AXTEL; BAUMHART; BLACK RIVER; SHINROCK; WASHINGTON → AXTEL; BAUMHART; BLACK RIVER; GREENFIELD; SHINROCK; WASHINGTON 2024-10-18 2026-07-17
Substations named AXTEL; BAUMHART; BLACK RIVER; GREENFIELD; SHINROCK; WASHINGTON → SHINROCK 2026-07-17 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-07-17 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 25
Black River – Shinrock 69 kV Line No role wording
69 kV
2024-10-18 SRRTEP Western
Item 04 - ATSI Supplemental Projects p. 4
Black River – Shinrock 69 kV Line No role wording
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.