Robbins substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
Target commercial operation dates as filed run from Sep 2011 to Jan 2023 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG1-059 | Robbins 138 kV | 138 | 60 | Solar | Withdrawn | Jan 2023 |
| R35 | Robbins Community Power | 138 | 50 | Other | Withdrawn | Sep 2011 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Westmoreland County, PA
- Yukon-Hatfield: 2 active, 940 MW of 2 filed
- Rhodes Lane: 1 active, 28 MW of 2 filed
- Westmoreland: 1 active, 13.2 MW of 5 filed
- Laurel: none active of 5 filed
- Yukon: none active of 2 filed
Other PJM queue substations in Cook County, IL
- Calumet: 3 active, 400 MW of 4 filed
- Chicago Heights: 1 active, 250 MW of 5 filed
- Burnham: 2 active, 200 MW of 2 filed
- Mount Rose: 1 active, 0.3 MW of 2 filed
- Crawford: none active of 3 filed
- Bloom: none active of 2 filed
- Clybourn: none active of 2 filed
- Hegewisch: none active of 2 filed
- I.C. Air Rights: none active of 2 filed
- River EC: none active of 2 filed