1 active project totalling 28 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
28active MW
2total filed
Queue IDProjectkVMWResourceStatus
Y2-080 Rhodes Lane 500kV 500 1,065 Gas Withdrawn
C01-1267 Rhodes Lane 500 kV 500 28 Gas Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.