Substation Scout

Reusens substation interconnection queue

1 active project totaling 4 MW in the PJM queue, plus 2 with terminal status (shown grayed).

3 PJM queue filings name Reusens as the point of interconnection, all in VA.

Target commercial operation dates as filed run from Dec 2014 to Oct 2022 (3 filings).

Transmission owner as filed: AEP (1 filing).

1active projects
4active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG2-202 Reusens 12.47 kV 12.5 20 Battery Withdrawn Oct 2022
AB2-109 Reusens Hydro Electric Generating Plant 34.5 4 Hydro In Service Mar 2018
AA2-001 Reusens 34.5kV 34.5 2 Hydro Withdrawn Dec 2014

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Reusens” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in City of Lynchburg, VA

All 7 PJM queue filings in City of Lynchburg, VA.

Other PJM queue substations in Campbell County, VA

All 26 PJM queue filings in Campbell County, VA.

Site Scanner