Reusens Hydro Electric Generating Plant
PJM queue ID AB2-109
Reusens Hydro Electric Generating Plant (AB2-109) is listed in the PJM interconnection queue as a 4 MW hydro project in City of Lynchburg, VA. The filing names Reusens as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of March 31, 2018.
| Queue ID | AB2-109 |
|---|---|
| Project name | Reusens Hydro Electric Generating Plant |
| Status (as published) | In Service |
| Substation | Reusens |
| Point of interconnection | Reusens 34.5kV |
| County | City of Lynchburg |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 4 MW |
| Resource (as published) | Hydro |
| Resource category | Hydro (normalized for filtering) |
| Target commercial operation | 2018-03-31 |
| Source dataset | serial |
Same substation and county
Reusens substation: 3 requests in the PJM queue, 1 active totaling 4 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG2-202 | Reusens 12.47 kV | 20 | Battery | Withdrawn |
| AA2-001 | Reusens 34.5kV | 2 | Hydro | Withdrawn |
City of Lynchburg, VA: 7 requests in the PJM queue, 1 active totaling 4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 12.5 |
| MW capacity | 4 |
| MFO | 12.5 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.