Earleys substation interconnection queue

3 active projects totalling 67 MW in the PJM queue, plus 7 with terminal status (shown greyed).

3active projects
67active MW
10total filed
Queue IDProjectkVMWResourceStatus
U1-031 Earleys 230kV 230 80 Other Withdrawn
AA1-065 Aulander Holloman Solar Park 230 53.6 Solar In Service
AD2-013 Earleys 115 kV 115 52.4 Solar Withdrawn
AE1-035 Aulander Holloman Solar Park 230 13.4 Solar In Service
W1-057 Earleys 34.5kV 34.5 7.6 Solar Withdrawn
AE2-151 Kruger Energy Hertford 34.5 6.5 Solar Withdrawn
AB2-087 Earleys 34.5kV 34.5 3.4 Solar Withdrawn
AB2-073 Earleys 230kV 230 0 Solar Withdrawn
AC2-063 Earleys 230kV 230 0 Solar Withdrawn
AG2-238 Earleys 230 kV 230 0 Battery Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.