Hertford, NC interconnection queue

7 active projects totalling 82.1 MW in the PJM queue, plus 23 with terminal status (shown greyed).

7active projects
82.1active MW
30total filed
Queue IDProjectkVMWResourceStatus
AF2-046 Murphy Solar 115 83.7 Solar Withdrawn
AG1-008 Bells Solar 115 83.7 Solar Withdrawn
U1-031 Earleys 230kV 230 80 Other Withdrawn
AA1-065 Aulander Holloman Solar Park 230 53.6 Solar In Service
AD2-013 Earleys 115 kV 115 52.4 Solar Withdrawn
AD2-051 Earleys – Northampton 230kV 230 52.4 Solar Withdrawn
AE1-019 Earleys-Scotland Neck 115 kV 115 42 Solar Withdrawn
AA2-118 Murphy-Tunis 115kV 115 14 Solar Withdrawn
AA2-164 Murphy 34.5kV 34.5 14 Solar Withdrawn
AE1-035 Aulander Holloman Solar Park 230 13.4 Solar In Service
AF2-264 Tunis 34.5 kV 34.5 13.4 Solar Withdrawn
AG1-082 NC1 Ahoskie Central Solar Project 34.5 12 Hybrid Withdrawn
AG1-083 Ahoskie 34.5 kV 34.5 12 Hybrid Withdrawn
AC1-163 Ahoskie 34.5KV 34.5 11.5 Solar Withdrawn
AG1-084 Earlys 34.5 kV 34.5 10.5 Hybrid Withdrawn
AG1-085 Earlys 34.5 n/r 10.5 Hybrid Withdrawn
AE2-346 Colice Hall Solar 34.5 8.4 Solar In Service
W1-057 Earleys 34.5kV 34.5 7.6 Solar Withdrawn
Y1-060 Aulander 34.5kV 34.5 7.5 Solar Withdrawn
AE2-151 Kruger Energy Hertford 34.5 6.5 Solar Withdrawn
AG1-035 Ahoskie 34.5 kV 34.5 6 Solar Withdrawn
AB2-099 Colice Hall Solar 34.5 3.5 Solar In Service
AB2-087 Earleys 34.5kV 34.5 3.4 Solar Withdrawn
V4-068 Murphy's 34.5kV 34.5 3.2 Solar In Service
AG1-037 NC3 Ahoskie South Solar Project 34.5 3 Hybrid Withdrawn
AB2-073 Earleys 230kV 230 0 Solar Withdrawn
AB2-148 Mapleton-Murphy 115kV 115 0 Solar Withdrawn
AB2-151 Mapleton-Murphy 115kV 115 0 Solar Withdrawn
AG2-238 Earleys 230 kV 230 0 Battery Active
AH1-091 Ahoskie 34.5kV 34.5 0 Battery Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.