Tunis substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Tunis as the point of interconnection, all in NC.
Target commercial operation dates as filed run from Dec 2021 to Mar 2023 (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-264 | Tunis 34.5 kV | 34.5 | 13.4 | Solar | Withdrawn | Mar 2023 |
| AG1-036 | Tunis 34.5 kV | 34.5 | 8.1 | Solar | Withdrawn | Dec 2021 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “Tunis” in NC. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- Tunis: Expansion Tracker, PJM planning: DOM state not printed
Other PJM queue substations in Hertford County, NC
- Earleys: 2 active, 67 MW of 10 filed
- Ahoskie: 2 active, 11.9 MW of 8 filed
- Mapleton-Murphy: none active of 2 filed
- Tunis-Mapleton: none active of 2 filed
Other PJM queue substations in Bertie County, NC
- Earleys: 2 active, 67 MW of 10 filed
- Cashie: 2 active, 66 MW of 9 filed
- Cashie-Trowbridge: 1 active, 51.8 MW of 3 filed
- Kelford: 2 active, 16.1 MW of 4 filed
- Cashie-Earleys: none active of 5 filed
- Earleys-Everetts: none active of 2 filed