Substation Scout

Earleys

Named in 5 PJM planning documents for 3 projects, from October 8, 2024 to October 8, 2025.

Existingdescribed as
DOMzone
115kV, 230kVkV as printed
7mentions

PJM interconnection queue

A PJM queue substation page has the same name: Earleys (NC) — 10 queue requests filed, 2 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Firetower Rd 230kV Delivery - DEV
DOM-2023-0015 · s3063
Under construction $5.0 M 02/29/2024 100 MW 2024-10-08
TEAC
230kV Line 246 – EOL Rebuild
DOM-2023-0044 · s3222.1
Conceptual $150.0 M 12/31/2028 36.7MW 2024-10-08
TEAC
Equipment Material Condition, Performance and Risk
DOM-2024-0013 · s3597
Conceptual $50M 12/31/2028 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named AHOSKIE; EARLEYS → AHOSKIE; EARLEYS; TUNIS 2024-10-17 2024-12-12

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 128
Firetower Rd 230kV Delivery - DEV “Line #246 (Earleys – Suffolk)”
2026-09-08* SRRTEP Southern
Dominion p. 153
230kV Line 246 – EOL Rebuild “Line #246 (Suffolk to Earleys)”
230kV
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 22
Equipment Material Condition, Performance and Risk No role wording
2024-12-12 SRRTEP Southern
Item 03 - DOM Supplemental Projects p. 3
Equipment Material Condition, Performance and Risk No role wording
2024-10-17 SRRTEP Southern
Item 01 - DOM Supplemental Projects p. 3
Equipment Material Condition, Performance and Risk No role wording
115kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 128
Firetower Rd 230kV Delivery - DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 153
230kV Line 246 – EOL Rebuild No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this