Substation Scout

Dresden 345 kV

PJM queue ID C01-1053

Dresden 345 kV (C01-1053) is listed in the PJM interconnection queue as a 32 MW nuclear project in Grundy County, IL. The filing names Dresden as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of November 15, 2028.

Queue IDC01-1053
Project nameDresden 345 kV
Status (as published)Active
SubstationDresden
Point of interconnectionDresden 345 kV
CountyGrundy
StateIL
Voltage345 kV
Capacity32 MW
Resource (as published)Nuclear
Resource categoryNuclear (normalized for filtering)
Target commercial operation2028-11-15
Source datasetcycle

Same substation and county

Dresden substation: 6 requests in the PJM queue, 4 active totaling 175 MW.

Queue IDProjectMWResourceStatus
Q49Dresden Nuclear Generating Station U270NuclearIn Service
Q50Dresden Nuclear Station Unit 370NuclearIn Service
X1-045Dresden Nuclear Generation Station, Units 2 & 33NuclearIn Service
AH2-421Dresden 138kV230BatteryWithdrawn
X3-045Dresden32NuclearWithdrawn

Grundy, IL: 44 requests in the PJM queue, 18 active totaling 3,015.2 MW.

A substation with the same name is named in PJM transmission planning materials: Dresden (COMED, 6 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperConstellation Energy Generation, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy32.0
MW capacity32.0
MFO1949.0
Submitted date4/24/2026
Last updated5/29/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first