PJM queue ID AE1-209

Queue IDAE1-209
Project nameHeadwaters Wind Farm III
Status (as published)Suspended
SubstationDesoto
Point of interconnectionDesoto 345 kV
CountyRandolph
StateIN
Voltage345 kV
Capacity13 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2026-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity13
Mfo100

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.