Delaware-Van Buren substation interconnection queue

3 active projects totaling 97.8 MW in the PJM queue, plus 1 with terminal status (shown grayed).

4 PJM queue filings name Delaware-Van Buren as the point of interconnection, all in Delaware County, IN.

Target commercial operation dates as filed run from Dec 2025 to Dec 2030 (4 filings). 3 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (2 filings).

3active projects
97.8active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE1-208 Meadow Forge Solar Energy Center 138 55 Solar Suspended Nov 2026
AH1-307 Delaware-Van Buren 138 kV 138 50 Battery Withdrawn Dec 2025
AE2-169 Meadow Forge Solar Energy Center 138 33 Solar Suspended Nov 2026
AH1-304 Delaware-Van Buren 138 kV 138 9.8 Solar Active Dec 2030

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Delaware County, IN

All 22 PJM queue filings in Delaware County, IN.