Substation Scout

Correctional substation interconnection queue

1 active project totalling 13.8 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
13.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
AH2-083 Correctional n/r 140 Battery Withdrawn
AB2-024 Correctional 34.5kV 34.5 13.8 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.