Substation Scout

Lanexa substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AG2-309 Lanexa 230 kV 230 150 Battery Withdrawn
AH1-231 Lanexa 230kV 230 28.8 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.