Basin - Chesterfield 230 kV

PJM queue ID C01-1543

Basin - Chesterfield 230 kV (C01-1543) is listed in the PJM interconnection queue as a 120 MW battery project in Chesterfield County, VA. The filing names Basin - Chesterfield as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of May 1, 2031.

Queue IDC01-1543
Project nameBasin - Chesterfield 230 kV
Status (as published)Active
SubstationBasin - Chesterfield
Point of interconnectionBasin - Chesterfield 230 kV
CountyChesterfield
StateVA
Voltage230 kV
Capacity120 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2031-05-01
Source datasetcycle

Same substation and county

Basin - Chesterfield substation: 2 requests in the PJM queue, 2 active totaling 545 MW.

Queue IDProjectMWResourceStatus
C01-2171Basin - Chesterfield 230 kV425NuclearActive

Chesterfield, VA: 41 requests in the PJM queue, 21 active totaling 2,439.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperGemini Power Project LLC
Transmission ownerDominion
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy120.0
MW capacity120.0
MFO120.0
Submitted date4/27/2026
Last updated9/1/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first