Substation Scout

CIA

Named in 2 PJM planning documents for 1 project, from September 8, 2026 to October 6, 2026.

Not stateddescribed as
DOMzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Line #2035 EOL Partial Rebuild
DOM-2026-0036
Conceptual $44M 03/15/2029 60MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 14 - DOM Supplemental Projects - Presentation p. 9
Dominion Transmission Zone: Supplemental Line #2035 EOL Partial Rebuild No role wording
2026-09-08 TEAC
Item 10 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Line #2035 EOL Partial Rebuild No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.