Substation Scout

Springboro-Venango Junction substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AF1-170 Springboro-Venango Junction 115 kV 115 46.5 Solar Withdrawn
AG1-455 Springboro-Venango Junction 115 kV 115 35 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.