Substation Scout

Fayette Energy Facility

PJM queue ID AA2-139

Fayette Energy Facility (AA2-139) is listed in the PJM interconnection queue as a 45 MW gas project in Fayette County, PA. The filing names Ronco as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 1, 2017.

Queue IDAA2-139
Project nameFayette Energy Facility
Status (as published)In Service
SubstationRonco
Point of interconnectionRonco 500kV
CountyFayette
StatePA
Voltage500 kV
Capacity45 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2017-10-01
Source datasetserial

Same substation and county

Ronco substation: 3 requests in the PJM queue, 2 active totaling 665 MW.

Queue IDProjectMWResourceStatus
E17_W27Ronco CT1, CT2, STG620GasIn Service
AF2-029Fayette Energy Facility8BatteryWithdrawn

Fayette, PA: 56 requests in the PJM queue, 20 active totaling 6,162.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy45
MW capacity45
MFO706

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first