Substation Scout

Reynolds substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 4 with terminal status (shown grayed).

4 PJM queue filings name Reynolds as the point of interconnection, all in IN.

Target commercial operation dates as filed run from Oct 2020 to Dec 2023 (4 filings).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE1-215 Reynolds 345 kV 345 395 Hybrid Withdrawn Dec 2023
AE1-216 Reynolds 345 kV 345 395 Hybrid Withdrawn Dec 2023
AE1-197 Reynolds 345 kV 345 65 Wind Withdrawn Sep 2021
AE1-211 Reynolds 345 kV 345 40 Wind Withdrawn Oct 2020

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Reynolds” in IN. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in White County, IN

All 37 PJM queue filings in White County, IN.

Other PJM queue substations in Jasper County, IN

All 3 PJM queue filings in Jasper County, IN.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first