Substation Scout

Reynolds

Named in 3 PJM planning documents for 1 project, from December 3, 2024 to October 8, 2025.

Not stateddescribed as
AEPzone
345kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone M-3 Process Western Indiana and Central Ohio
AEP-2023-IM015 · s3594.1
Not printed $452.64 M 05/30/2031 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 18
AEP Transmission Zone M-3 Process Western Indiana and Central Ohio No role wording
345kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 19
AEP Transmission Zone M-3 Process Western Indiana and Central Ohio No role wording
345kV
2024-12-03 TEAC
Item 08 - AEP Supplemental Projects p. 9
AEP Transmission Zone M-3 Process Western Indiana and Central Ohio No role wording
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.