Fleming, KY interconnection queue

5 active projects totalling 281.4 MW in the PJM queue, plus 7 with terminal status (shown greyed).

5active projects
281.4active MW
12total filed
Queue IDProjectkVMWResourceStatus
AF1-233 Fleming Solar 138 113.1 Solar EP
AH1-664 Goddard-Plumville 138 kV 138 66.8 Solar Active
C01-1450 GODDARD - PLUMVILLE 138 kV 138 65 Solar Withdrawn
AH2-383 Goddard - Flemingsburg 138 kV 138 56 Hybrid Withdrawn
AH1-429 Flemingsburg - Spurlock 138 kV 138 54 Solar Withdrawn
AH1-665 Goddard-Plumsville 138 kV II 138 53.5 Solar Active
AI1-133 Hillsboro 69 kV 69 50 Hybrid Withdrawn
AH1-666 Flemingsburg - Spurlock 138 kV 138 48 Solar Active
AH1-430 Flemingsburg - Spurlock 138 kV 138 36 Battery Withdrawn
AI2-123 Goddard - Plumville 138 kV 138 35 Solar Withdrawn
AI2-124 Goddard 138 kV 138 23.3 Solar Withdrawn
C01-1060 Flemingsburg 12 kV 12 0 Solar Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.