Substation Scout

Flemingsburg substation interconnection queue

1 active project totaling 0 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Flemingsburg as the point of interconnection, all in KY.

Target commercial operation dates as filed run from Dec 2015 to Sep 2027 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: EKPC (1 filing).

1active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
Y3-031A_EKPC2 Flemingsburg 138 KV 138 19.5 Wind Withdrawn Dec 2015
C01-1060 Flemingsburg 12 kV 12 0 Solar Active Sep 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Fleming County, KY

All 12 PJM queue filings in Fleming County, KY.