Gunn Road substation interconnection queue

2 active projects totalling 74 MW in the PJM queue, plus 2 with terminal status (shown greyed).

2active projects
74active MW
4total filed
Queue IDProjectkVMWResourceStatus
AF1-285 Scioto Solar 345 56 Hybrid Under Construction
AI2-452 Gunn Road 345 kV 345 51.8 Solar Withdrawn
AC2-124 Gunn Road 345kV 345 19 Solar Withdrawn
AE2-306 Scioto Solar 345 18 Solar Under Construction

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.