Home / PJM / substation / Gunn Road
Gunn Road substation interconnection queue
2 active projects
totalling 74 MW in the PJM queue, plus 2 with terminal status (shown greyed).
2 active projects
74 active MW
4 total filed
Queue ID Project kV MW Resource Status
AF1-285
Scioto Solar
345
56
Hybrid
Under Construction
AI2-452
Gunn Road 345 kV
345
51.8
Solar
Withdrawn
AC2-124
Gunn Road 345kV
345
19
Solar
Withdrawn
AE2-306
Scioto Solar
345
18
Solar
Under Construction
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with PJM before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.