Gunn Road substation interconnection queue
2 active projects totalling 74 MW in the PJM queue, plus 2 with terminal status (shown greyed).
2active projects
74active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AF1-285 | Scioto Solar | 345 | 56 | Hybrid | Under Construction |
| AI2-452 | Gunn Road 345 kV | 345 | 51.8 | Solar | Withdrawn |
| AC2-124 | Gunn Road 345kV | 345 | 19 | Solar | Withdrawn |
| AE2-306 | Scioto Solar | 345 | 18 | Solar | Under Construction |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.