Hardin, OH interconnection queue

18 active projects totalling 715 MW in the PJM queue, plus 21 with terminal status (shown greyed).

18active projects
715active MW
39total filed
Queue IDProjectkVMWResourceStatus
AG1-562 Taylor Creek 345 150 Solar Withdrawn
AH1-767 Not reported n/r 140 Battery Withdrawn
AD2-086 Hardin Energy Center – Phase 3 345 138 Solar In Service
AD1-130 Hardin Energy Center – Phase 2 345 101.5 Solar In Service
AI2-309 Marysville-Gunn Road 345 kV 345 90.5 Solar Withdrawn
AI2-149 Hardin Switch 345 kV 345 67.2 Solar Withdrawn
C01-1653 Hardin Switch 345 kV 345 67.2 Solar Active
T142 Van Wert II 345 60 Wind Withdrawn
AF1-285 Scioto Solar 345 56 Hybrid Under Construction
AE2-216 Hardin Energy Center – Storage II 345 55 Battery Suspended
AI2-452 Gunn Road 345 kV 345 51.8 Solar Withdrawn
AD2-091 Hardin Energy Center – Storage I 345 50 Battery Suspended
AB2-170 Hardin Energy Center 345 49.4 Solar In Service
AE1-091 Strawhat Solar Energy Center 138 46.9 Solar Suspended
AI2-270 East Lima-Marysville 345kV 345 45 Solar Withdrawn
AG1-554 Scioty Solar 138 32.7 Solar Engineering and Procurement
U2-072 Scioto Ridge Wind Farm 345 32.5 Wind In Service
AI2-107 Ada-Dunkirk 69kV 69 31.7 Wind Withdrawn
AI2-181 Hardin Switch 345 kV 345 27.8 Solar Withdrawn
C01-1652 Hardin Switch 345 kV 345 27.8 Solar Active
AI2-173 West Newton-Lynn 138 kV 138 26.4 Solar Withdrawn
U2-042 East Lima-South Kenton 138kV 138 26.1 Wind Withdrawn
U2-066 Marysville-SW Lima 345kV 345 26 Wind Withdrawn
AH1-539 South Kenton 138 kV 138 25.9 Hybrid Withdrawn
N38 W. Newton-Lynn 138kV 138 24 Wind Withdrawn
U2-041 Hardin Wind Farm 345 21.7 Wind Withdrawn
U1-060 East Lima-South Kenton 138kV 138 19.7 Wind Withdrawn
AH1-326 West Newton - Lynn 138 kV 138 19.1 Solar Withdrawn
AC2-124 Gunn Road 345kV 345 19 Solar Withdrawn
AE2-306 Scioto Solar 345 18 Solar Under Construction
AI2-194 South Kenton 138 kV 138 15.8 Solar Withdrawn
AE1-090 Hardin Energy Center - Phase 3 345 12 Solar In Service
U1-059 Hog Creek Wind Farm 69 9.6 Wind In Service
AC1-195 Dunkirk-Ada 69kV 69 9 Wind Withdrawn
AH1-327 Hardin Switch 345 kV 345 8.4 Solar Active
V3-028 Hardin Energy Center 345 7.6 Solar In Service
W1-056 Hog Creek Wind Farm 69 2.4 Wind In Service
AA2-186 Forest 69kV 69 0 Battery Withdrawn
C01-1064 Ada 12.47 kV 12.5 0 Solar Active