Hardin, OH interconnection queue
18 active projects totalling 715 MW in the PJM queue, plus 21 with terminal status (shown greyed).
18active projects
715active MW
39total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG1-562 | Taylor Creek | 345 | 150 | Solar | Withdrawn |
| AH1-767 | Not reported | n/r | 140 | Battery | Withdrawn |
| AD2-086 | Hardin Energy Center – Phase 3 | 345 | 138 | Solar | In Service |
| AD1-130 | Hardin Energy Center – Phase 2 | 345 | 101.5 | Solar | In Service |
| AI2-309 | Marysville-Gunn Road 345 kV | 345 | 90.5 | Solar | Withdrawn |
| AI2-149 | Hardin Switch 345 kV | 345 | 67.2 | Solar | Withdrawn |
| C01-1653 | Hardin Switch 345 kV | 345 | 67.2 | Solar | Active |
| T142 | Van Wert II | 345 | 60 | Wind | Withdrawn |
| AF1-285 | Scioto Solar | 345 | 56 | Hybrid | Under Construction |
| AE2-216 | Hardin Energy Center – Storage II | 345 | 55 | Battery | Suspended |
| AI2-452 | Gunn Road 345 kV | 345 | 51.8 | Solar | Withdrawn |
| AD2-091 | Hardin Energy Center – Storage I | 345 | 50 | Battery | Suspended |
| AB2-170 | Hardin Energy Center | 345 | 49.4 | Solar | In Service |
| AE1-091 | Strawhat Solar Energy Center | 138 | 46.9 | Solar | Suspended |
| AI2-270 | East Lima-Marysville 345kV | 345 | 45 | Solar | Withdrawn |
| AG1-554 | Scioty Solar | 138 | 32.7 | Solar | Engineering and Procurement |
| U2-072 | Scioto Ridge Wind Farm | 345 | 32.5 | Wind | In Service |
| AI2-107 | Ada-Dunkirk 69kV | 69 | 31.7 | Wind | Withdrawn |
| AI2-181 | Hardin Switch 345 kV | 345 | 27.8 | Solar | Withdrawn |
| C01-1652 | Hardin Switch 345 kV | 345 | 27.8 | Solar | Active |
| AI2-173 | West Newton-Lynn 138 kV | 138 | 26.4 | Solar | Withdrawn |
| U2-042 | East Lima-South Kenton 138kV | 138 | 26.1 | Wind | Withdrawn |
| U2-066 | Marysville-SW Lima 345kV | 345 | 26 | Wind | Withdrawn |
| AH1-539 | South Kenton 138 kV | 138 | 25.9 | Hybrid | Withdrawn |
| N38 | W. Newton-Lynn 138kV | 138 | 24 | Wind | Withdrawn |
| U2-041 | Hardin Wind Farm | 345 | 21.7 | Wind | Withdrawn |
| U1-060 | East Lima-South Kenton 138kV | 138 | 19.7 | Wind | Withdrawn |
| AH1-326 | West Newton - Lynn 138 kV | 138 | 19.1 | Solar | Withdrawn |
| AC2-124 | Gunn Road 345kV | 345 | 19 | Solar | Withdrawn |
| AE2-306 | Scioto Solar | 345 | 18 | Solar | Under Construction |
| AI2-194 | South Kenton 138 kV | 138 | 15.8 | Solar | Withdrawn |
| AE1-090 | Hardin Energy Center - Phase 3 | 345 | 12 | Solar | In Service |
| U1-059 | Hog Creek Wind Farm | 69 | 9.6 | Wind | In Service |
| AC1-195 | Dunkirk-Ada 69kV | 69 | 9 | Wind | Withdrawn |
| AH1-327 | Hardin Switch 345 kV | 345 | 8.4 | Solar | Active |
| V3-028 | Hardin Energy Center | 345 | 7.6 | Solar | In Service |
| W1-056 | Hog Creek Wind Farm | 69 | 2.4 | Wind | In Service |
| AA2-186 | Forest 69kV | 69 | 0 | Battery | Withdrawn |
| C01-1064 | Ada 12.47 kV | 12.5 | 0 | Solar | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.