Ada-Dunkirk substation interconnection queue
2 active projects totalling 12 MW in the PJM queue, plus 1 with terminal status (shown greyed).
2active projects
12active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AI2-107 | Ada-Dunkirk 69kV | 69 | 31.7 | Wind | Withdrawn |
| U1-059 | Hog Creek Wind Farm | 69 | 9.6 | Wind | In Service |
| W1-056 | Hog Creek Wind Farm | 69 | 2.4 | Wind | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.