Substation Scout

Ada-Dunkirk substation interconnection queue

2 active projects totalling 12 MW in the PJM queue, plus 1 with terminal status (shown greyed).

2active projects
12active MW
3total filed
Queue IDProjectkVMWResourceStatus
AI2-107 Ada-Dunkirk 69kV 69 31.7 Wind Withdrawn
U1-059 Hog Creek Wind Farm 69 9.6 Wind In Service
W1-056 Hog Creek Wind Farm 69 2.4 Wind In Service

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.