Ada-Dunkirk substation interconnection queue
2 active projects totaling 12 MW in the PJM queue, plus 1 with terminal status (shown grayed).
3 PJM queue filings name Ada-Dunkirk as the point of interconnection, all in Hardin County, OH.
Target commercial operation dates as filed run from Dec 2017 to Feb 2023 (3 filings).
2active projects
12active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI2-107 | Ada-Dunkirk 69kV | 69 | 31.7 | Wind | Withdrawn | Feb 2023 |
| U1-059 | Hog Creek Wind Farm | 69 | 9.6 | Wind | In Service | Dec 2017 |
| W1-056 | Hog Creek Wind Farm | 69 | 2.4 | Wind | In Service | Dec 2017 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Hardin County, OH
- Hardin Switch: 7 active, 409.9 MW of 9 filed
- East Lima-Marysville: 3 active, 89.5 MW of 6 filed
- Gunn Road: 2 active, 74 MW of 4 filed
- West Newton-Lynn: 1 active, 46.9 MW of 2 filed
- South Kenton: 1 active, 32.7 MW of 3 filed
- East Lima-South Kenton: none active of 3 filed
- Forest: none active of 3 filed
- Marysville-Gunn Road: none active of 2 filed