South Kenton substation interconnection queue
1 active project totaling 32.7 MW in the PJM queue, plus 2 with terminal status (shown grayed).
3 PJM queue filings name South Kenton as the point of interconnection, all in Hardin County, OH.
Target commercial operation dates as filed run from Jun 2025 to Mar 2028 (3 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: AEP (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG1-554 | Scioty Solar | 138 | 32.7 | Solar | Engineering and Procurement | Oct 2027 |
| AH1-539 | South Kenton 138 kV | 138 | 25.9 | Hybrid | Withdrawn | Mar 2028 |
| AI2-194 | South Kenton 138 kV | 138 | 15.8 | Solar | Withdrawn | Jun 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: South Kenton (AEP, 3 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Same name on other Substation Scout pages
Other sources that print a substation named “South Kenton” in OH. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
- South Kenton: Expansion Tracker, PJM planning: PJM system-wide state not printed
Other PJM queue substations in Hardin County, OH
- Hardin Switch: 7 active, 409.9 MW of 9 filed
- East Lima-Marysville: 3 active, 89.5 MW of 6 filed
- Gunn Road: 2 active, 74 MW of 4 filed
- West Newton-Lynn: 1 active, 46.9 MW of 2 filed
- Ada-Dunkirk: 2 active, 12 MW of 3 filed
- East Lima-South Kenton: none active of 3 filed
- Forest: none active of 3 filed
- Marysville-Gunn Road: none active of 2 filed