Substation Scout

Grassfield substation interconnection queue

1 active project totalling 12.6 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
12.6active MW
3total filed
Queue IDProjectkVMWResourceStatus
AF2-057 Cedar Energy Center 34.5 20 Battery Withdrawn
AB2-086 Grassfield 13.2kV 13.2 13 Solar Withdrawn
AC1-147 Grassfield 34.5kV 34.5 12.6 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.