Grassfield substation interconnection queue
1 active project
totalling 12.6 MW in the PJM queue, plus 2 with terminal status (shown greyed).
1 active projects
12.6 active MW
3 total filed
Queue ID Project kV MW Resource Status
AF2-057
Cedar Energy Center
34.5
20
Battery
Withdrawn
AB2-086
Grassfield 13.2kV
13.2
13
Solar
Withdrawn
AC1-147
Grassfield 34.5kV
34.5
12.6
Solar
In Service
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with PJM before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.