Grassfield 34.5kV
PJM queue ID AC1-147
Grassfield 34.5kV (AC1-147) is listed in the PJM interconnection queue as a 12.6 MW solar project in City of Chesapeake, VA. The filing names Grassfield as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2021.
| Queue ID | AC1-147 |
|---|---|
| Project name | Grassfield 34.5kV |
| Status (as published) | In Service |
| Substation | Grassfield |
| Point of interconnection | Grassfield 34.5kV |
| County | City of Chesapeake |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 12.6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2021-12-31 |
| Source dataset | serial |
Same substation and county
Grassfield substation: 3 requests in the PJM queue, 1 active totaling 12.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF2-057 | Cedar Energy Center | 20 | Battery | Withdrawn |
| AB2-086 | Grassfield 13.2kV | 13 | Solar | Withdrawn |
City of Chesapeake, VA: 50 requests in the PJM queue, 10 active totaling 1,016 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 20 |
| MW capacity | 12.6 |
| MFO | 20 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.