Garden Plain - Rock Falls substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Garden Plain - Rock Falls as the point of interconnection, all in IL.
Target commercial operation date as filed: Apr 2028 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI1-174 | Garden Plain - Rock Falls 138 kV | 138 | 94.4 | Hybrid | Withdrawn | Apr 2028 |
| AI1-171 | Garden Plain - Rock Falls 138 kV | 138 | 60 | Solar | Withdrawn | Apr 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Stephenson County, IL
- Wempletown: 2 active, 100 MW of 13 filed
- Lena: 3 active, 62 MW of 7 filed
- Lena - Freeport: 1 active, 14.4 MW of 2 filed
- Lancaster: none active of 4 filed
- Lancaster-Maryland: none active of 2 filed
- Lena - Lancaster: none active of 2 filed
Other PJM queue substations in Whiteside County, IL
- Cordova: 4 active, 265 MW of 6 filed
- Normandy: 3 active, 127.4 MW of 5 filed
- Garden Plain: 2 active, 53.6 MW of 5 filed
- Quad Cities: none active of 2 filed
Site Scanner