Garden Plain substation interconnection queue
2 active projects totaling 53.6 MW in the PJM queue, plus 3 with terminal status (shown grayed).
5 PJM queue filings name Garden Plain as the point of interconnection, all in Whiteside County, IL.
Target commercial operation dates as filed run from Dec 2026 to Apr 2031 (5 filings). 2 active filings target a date after November 27, 2026.
Transmission owner as filed: ComEd (3 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AH2-376 | Garden Plain 138 kV | 138 | 153 | Battery | Withdrawn | Oct 2027 |
| C01-1587 | Garden Plain 138 kV | 138 | 150 | Battery | Withdrawn | Apr 2031 |
| AH2-270 | Garden Plain 138 kV | 138 | 51 | Wind | Withdrawn | Dec 2026 |
| AF1-296 | Gipper Wind Farm | 138 | 33.6 | Wind | EP | Sep 2029 |
| C01-1588 | Garden Plain 138 kV | 138 | 20 | Wind | Active | Apr 2031 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Tracked changes at this substation
1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-10-05 | C01-1587 | Terminal status | 150 | Active → Withdrawn |
Other PJM queue substations in Whiteside County, IL
- Cordova: 4 active, 265 MW of 6 filed
- Normandy: 3 active, 127.4 MW of 5 filed
- Garden Plain - Rock Falls: none active of 2 filed
- Quad Cities: none active of 2 filed