Lena substation interconnection queue

3 active projects totaling 62 MW in the PJM queue, plus 4 with terminal status (shown grayed).

7 PJM queue filings name Lena as the point of interconnection, all in IL.

Target commercial operation dates as filed run from Mar 2009 to Sep 2024 (7 filings).

Transmission owner as filed: ComEd (2 filings).

3active projects
62active MW
7total filed
Queue IDProjectkVMWResourceStatusTarget COD
AH1-354 Lena 138 kV 138 40 Battery Withdrawn Sep 2024
R16 Lena 138kV 138 25.2 Wind Withdrawn Dec 2016
AD2-172 High Point Solar 138 21 Solar In Service Feb 2024
AE2-035 High Point II Solar 138 21 Solar In Service Feb 2024
P46 EcoGrove WF (67 WT) 138 20 Wind In Service Mar 2009
AH1-353 Lena 138 kV 138 12 Solar Withdrawn Sep 2024
AF1-060 Lena 138 kV 138 10.3 Battery Withdrawn Dec 2020

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Stephenson County, IL

All 26 PJM queue filings in Stephenson County, IL.

Other PJM queue substations in JoDaviess County, IL

All 3 PJM queue filings in JoDaviess County, IL.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first