Eldred substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 6 with terminal status (shown grayed).

6 PJM queue filings name Eldred as the point of interconnection, all in Schuylkill County, PA.

Target commercial operation dates as filed run from Nov 2006 to Jan 2033 (6 filings).

Transmission owner as filed: PPL (2 filings).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
Q89 Eldred 230kV 230 750 Coal Withdrawn Aug 2012
C01-1198 Eldred 230 kV 230 715 Gas Withdrawn Jan 2033
U1-086 Eldred 230kV 230 150 Other Withdrawn Jun 2010
AE2-295 Eldred 230 kV 230 25.7 Wind Withdrawn May 2022
AG1-060 Eldred 69 kV 69 25.7 Solar Withdrawn May 2022
N50 Eldred 230kV 230 18 Wind Withdrawn Nov 2006

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Eldred (PPL, 8 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Schuylkill County, PA

All 46 PJM queue filings in Schuylkill County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first