Eldred substation interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).
0active projects
0active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| Q89 | Eldred 230kV | 230 | 750 | Coal | Withdrawn |
| C01-1198 | Eldred 230 kV | 230 | 715 | Gas | Withdrawn |
| U1-086 | Eldred 230kV | 230 | 150 | Other | Withdrawn |
| AE2-295 | Eldred 230 kV | 230 | 25.7 | Wind | Withdrawn |
| AG1-060 | Eldred 69 kV | 69 | 25.7 | Solar | Withdrawn |
| N50 | Eldred 230kV | 230 | 18 | Wind | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.