Substation Scout

Eldred substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
Q89 Eldred 230kV 230 750 Coal Withdrawn
C01-1198 Eldred 230 kV 230 715 Gas Withdrawn
U1-086 Eldred 230kV 230 150 Other Withdrawn
AE2-295 Eldred 230 kV 230 25.7 Wind Withdrawn
AG1-060 Eldred 69 kV 69 25.7 Solar Withdrawn
N50 Eldred 230kV 230 18 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.