Port Carbon substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
W1-114 East Norwegian Township Solar I n/r 1.1 Solar Withdrawn
W2-081 Port Carbon 12kV 12 1.1 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.