Substation Scout

Dryburg 115 kV

PJM queue ID AG2-262

Queue IDAG2-262
Project nameDryburg 115 kV
Status (as published)Active
SubstationDryburg
Point of interconnectionDryburg 115 kV
CountyHalifax
StateVA
Voltage115 kV
Capacity6.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-31
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperStaunton Solar LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StagePhase 3
Mw Energy11.0
Mw Capacity6.6
Mfo47.0
Submitted Date3/18/2021
Last Updated8/18/2026