Substation Scout

Church substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
AG2-281 Church 138 kV 138 50 Battery Withdrawn
AF2-109 Church 69 kV 69 10 Battery Withdrawn
W3-061 Church 69kV 69 7.6 Solar Withdrawn
Z2-097 Church 25 3.5 Solar Withdrawn
V4-039 Church n/r 3.4 Solar Withdrawn
Z1-081 Sunfish Solar Project 25 2.3 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.