Substation Scout

Church substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 6 with terminal status (shown grayed).

6 PJM queue filings name Church as the point of interconnection, all in MD.

Target commercial operation dates as filed run from May 2011 to Nov 2027 (6 filings).

Transmission owner as filed: DPL (1 filing).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG2-281 Church 138 kV 138 50 Battery Withdrawn Nov 2027
AF2-109 Church 69 kV 69 10 Battery Withdrawn Oct 2022
W3-061 Church 69kV 69 7.6 Solar Withdrawn May 2011
Z2-097 Church 25 3.5 Solar Withdrawn Sep 2019
V4-039 Church n/r 3.4 Solar Withdrawn Jun 2011
Z1-081 Sunfish Solar Project 25 2.3 Solar Withdrawn Jul 2017

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Queen Anne's County, MD

All 45 PJM queue filings in Queen Anne's County, MD.

Other PJM queue substations in Kent County, MD

All 16 PJM queue filings in Kent County, MD.