Church-Wye Mills substation interconnection queue
2 active projects totaling 21.2 MW in the PJM queue.
2 PJM queue filings name Church-Wye Mills as the point of interconnection, all in Queen Anne's County, MD.
Target commercial operation date as filed: Dec 2023 (2 filings).
2active projects
21.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AB2-032 | Pondtown Solar 2 | 138 | 13.6 | Solar | In Service | Dec 2023 |
| AB2-153 | Pondtown Solar 2 | 138 | 7.6 | Solar | In Service | Dec 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Queen Anne's County, MD
- Wye Mills: 1 active, 3.8 MW of 5 filed
- Church Hill: 1 active, 2.3 MW of 2 filed
- Price: 1 active, 0.8 MW of 9 filed
- Church: none active of 6 filed
- Kings Creek: none active of 6 filed
- Carville: none active of 3 filed
- Centreville: none active of 3 filed