Carville substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name Carville as the point of interconnection, all in Queen Anne's County, MD.
Target commercial operation dates as filed run from Dec 2023 to Dec 2025 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-619 | Carville 138 kV | 138 | 102.5 | Solar | Withdrawn | Dec 2023 |
| AH1-620 | Carville 138kV | 138 | 45.6 | Solar | Withdrawn | Dec 2025 |
| AD2-076 | Concho Solar I | 138 | 18.6 | Solar | Withdrawn | Jun 2024 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Queen Anne's County, MD
- Church-Wye Mills: 2 active, 21.2 MW of 2 filed
- Wye Mills: 1 active, 3.8 MW of 5 filed
- Church Hill: 1 active, 2.3 MW of 2 filed
- Price: 1 active, 0.8 MW of 9 filed
- Church: none active of 6 filed
- Kings Creek: none active of 6 filed
- Centreville: none active of 3 filed