Price substation interconnection queue
1 active project totaling 0.8 MW in the PJM queue, plus 8 with terminal status (shown grayed).
9 PJM queue filings name Price as the point of interconnection, all in Queen Anne's County, MD.
Target commercial operation dates as filed run from Jul 2017 to Oct 2024 (9 filings).
1active projects
0.8active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-586 | Price 69 kV | 69 | 18.6 | Solar | Withdrawn | Jun 2024 |
| AC1-220 | Price 25kV | 25 | 15.5 | Solar | Withdrawn | Sep 2018 |
| AF2-313 | Price 69 kV | 69 | 12.7 | Solar | Withdrawn | Aug 2021 |
| AG2-295 | Price 25 kV | 25 | 9.3 | Solar | Withdrawn | Oct 2023 |
| AH1-253 | Price 69kV | 69 | 9.3 | Solar | Withdrawn | Oct 2024 |
| AB2-063 | Price 69kV | 69 | 7.6 | Solar | Withdrawn | Dec 2018 |
| AB1-162 | Price 69 kV | 69 | 6.3 | Solar | Withdrawn | Jul 2017 |
| AI2-211 | Price 25 kV | 25 | 2.6 | Solar | Withdrawn | Mar 2023 |
| AF1-259 | Church Hill Solar | 25 | 0.8 | Solar | In Service | Sep 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Queen Anne's County, MD
- Church-Wye Mills: 2 active, 21.2 MW of 2 filed
- Wye Mills: 1 active, 3.8 MW of 5 filed
- Church Hill: 1 active, 2.3 MW of 2 filed
- Church: none active of 6 filed
- Kings Creek: none active of 6 filed
- Carville: none active of 3 filed
- Centreville: none active of 3 filed