Substation Scout

Quakertown Solar Farm

PJM queue ID AD2-026

Quakertown Solar Farm (AD2-026) is listed in the PJM interconnection queue as a 4.1 MW solar project in Hunterdon County, NJ. The filing names East Flemington-Frenchtown II as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2020.

Queue IDAD2-026
Project nameQuakertown Solar Farm
Status (as published)In Service
SubstationEast Flemington-Frenchtown II
Point of interconnectionEast Flemington-Frenchtown 34.5 kV II
CountyHunterdon
StateNJ
Voltage34.5 kV
Capacity4.1 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2020-12-31
Source datasetserial

Same substation and county

Hunterdon, NJ: 89 requests in the PJM queue, 26 active totaling 863.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0
MW capacity4.1
MFO8.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.