Substation Scout

Prince William, VA interconnection queue

14 active projects totalling 644 MW in the PJM queue, plus 25 with terminal status (shown greyed).

14active projects
644active MW
39total filed
Queue IDProjectkVMWResourceStatus
E22 Burches Hill 500kV 500 960 Gas Withdrawn
V1-031 Possum Point 230kV 230 875 Gas Withdrawn
T180 Gainesville 230kV 230 650 Gas Withdrawn
P08 Possum Point n/r 600 Gas Withdrawn
X4-013 Pleasant View-Edwards Ferry 230kV 230 200 Not reported Withdrawn
AG2-113 Nokesville-Vint Hill 230 kV 230 150 Battery Withdrawn
AG2-284 Catharpin 230 kV 230 150 Battery Withdrawn
AG2-304 Liberty 230 kV 230 150 Battery Withdrawn
AG2-306 Possum Point 230 kV 230 150 Battery Withdrawn
C01-1933 Liberty 230 kV 230 145 Battery Active
AI2-231 Gainesville-Loudoun 230 kV 230 120 Battery Withdrawn
AH2-034 Possum Point 230kV 230 100 Battery Withdrawn
AH2-035 Possum Point 500kV 500 100 Battery Withdrawn
C01-1128 Possum Point 230 kV 230 100 Battery Active
AH1-741 Not reported n/r 97 Gas Withdrawn
AH1-696 Possum Point 230kV 230 94 Gas Active
AG1-143 Gainesville-Loudoun 230 kV 230 80 Battery Withdrawn
AH2-032 Possum Point 115kV 115 60 Battery Withdrawn
AH2-033 Possum Point 115kV 115 60 Battery Withdrawn
C01-1127 Possum Point 115 kV 115 60 Battery Active
C01-1259 Possum Point 115 kV 115 60 Battery Active
R80 Possum Point Unit 6 230 60 Gas In Service
AH2-060 Possum Point 230 kV 230 55 Battery Withdrawn
AH2-061 Possum Point 230 kV II 230 55 Battery Withdrawn
C01-1264 Possum Point 230 kV 230 55 Battery Active
AH2-058 Possum Point 115 kV 115 30 Battery Withdrawn
AH2-059 Possum Point 115 kV II 115 30 Battery Withdrawn
C01-1263 Possum Point 115 kV 115 30 Battery Active
AG2-065 River Ridge 34.5 kV 34.5 20 Battery Withdrawn
AH1-126 Bowman 12.5kV 12.5 20 Battery Withdrawn
C01-1294 Liberty 115 kV 115 20 Battery Active
C01-1295 Liberty 115 kV 115 20 Battery Active
S99 Possum Point 230kV 230 20 Other Withdrawn
AC2-072 Nokesville 35 13.3 Solar Withdrawn
AA2-079 Possum Point Unit 6 230 0 Gas In Service
AA2-185 Independent Hill 115kV 115 0 Gas Withdrawn
AH1-124 Reid Energy Center 34.5 0 Battery UC
AH1-127 Railroad Energy Center 34.5 0 Battery UC
AH1-128 Bethlehem Energy Center 34.5 0 Battery UC

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.