Babcock

Named in 4 PJM planning documents for 1 project, from December 3, 2024 to October 6, 2026.

Existingdescribed as
AEPzone
345kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Greentown, IN
AEP-2024-IM018 · s3608.1-7
Conceptual $0M (PJM) 2032-2034 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $173M → $0M (PJM) 2025-03-04 2026-10-06
In-service date 06/01/2032 → 2032-2034 2024-12-03 2025-03-04
Substations named BABCOCK; DRESSER; FAIRBANKS; GREEN ACRES; GREENTOWN; GWYNNEVILLE; HANNA; JEFFERSON; LULU; OLIVE; ROCKPORT; SORENSON; SULLIVAN; TANNERS CREEK; UNIVERSITY PARK → BABCOCK; BATESVILLE; DRESSER; FAIRBANKS; FALL CREEK; GREEN ACRES; GREENTOWN; GWYNNEVILLE; HANNA; JEFFERSON; LULU; MADISON COUNTY; OLIVE; PIKE COUNTY; ROCKPORT; SORENSON; SULLIVAN; SUNNYSIDE; TANNERS CREEK; UNIVERSITY PARK 2024-12-03 2025-03-04
Substations named BABCOCK; BATESVILLE; DRESSER; FAIRBANKS; FALL CREEK; GREEN ACRES; GREENTOWN; GWYNNEVILLE; HANNA; JEFFERSON; LULU; MADISON COUNTY; OLIVE; PIKE COUNTY; ROCKPORT; SORENSON; SULLIVAN; SUNNYSIDE; TANNERS CREEK; UNIVERSITY PARK → BABCOCK; BATESVILLE; GWYNNEVILLE; MADISON COUNTY; PIKE COUNTY; SORENSON; SULLIVAN 2025-03-04 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 5
Greentown, IN “existing Babcock 345kV substation”
345kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 7
Greentown, IN “cut into Babcock 345kV station”
345kV
2025-03-04 TEAC
Item 08 - AEP Supplemental Projects p. 3
Greentown, IN “existing Babcock 345kV substation”
345kV
2024-12-03 TEAC
Item 08 - AEP Supplemental Projects p. 4
Greentown, IN “existing Babcock 345kV substation”
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this